TLI Group were nominated by ESB Networks as PSCS for the safe co-ordination and project delivery for the removal of the T4201 Transformer (circa 350 tons) by Aylward Heavy Haulage Ltd from the 400kV Substation in Moneypoint to the Victrol Barge moored at an onsite jetty. From here the transformer was taken by barge to Foynes Port before the onward journey to Italy aboard the BBC vessel.
The scale and complexity in the delivery of this project required extremely detailed enabling works, planning and co-ordination. Special mention to TLI Group’s Danny Leen, who played a key part in coordinating the various key stakeholders to make this project a complete success on behalf of ESB Networks.
Well done to everyone involved.